Quantitative Reasoning Speed And Work Test Online

Speed And Work Test Online

Total Questions: 50
Time Allowed: 25 Minutes
Total Marks: 50
How to Attempt Test: Please choose the right Option in MCQ-type question.
Test Helpful For: Aptitude Test
Forces Test
Quantitative Reasoning Test
Interview Questions Answer
Recruitment Tests

Quantitative Reasoning Speed And Work Practice Test Online

 0%

Page 1 of 2

1. A can do a job in 15 days. B is 50% more efficient than A. In how many days B will finish it?

2. A car travels from P to Q at 60 km/h and returns at 40 km/h. Average speed of the car?

3. A train 120 m long crosses a bridge 180 m long in 12 sec. Speed of train is?

4. A and B can finish a piece of work in 20 days. They start together but after 8 days A leaves. B alone will finish the remaining in 30 days. How long will A take alone?

5. A does a piece of work in 20 days and B in 30 days. They work together for 5 days, then B leaves. Remaining work will be finished by A in?

6. A train 90 m long crosses a platform 150 m long in 12 seconds. Speed of the train is?

7. If 10 men can complete a piece of work in 15 days, in how many days will 15 men do it?

8. A pipe can fill a tank in 6 hours. Due to a leak it takes 8 hours. The leak alone will empty the tank in?

9. A can complete a work in 25 days. B can do it in 50 days. They start together but A leaves after 5 days. The remaining work will be finished by B in?

10. A can do a job in 12 days, B in 18 days and C in 36 days. They all work together for 3 days. How much work is left?

11. If A and B can finish a work in 10 days, B and C in 12 days, and A and C in 15 days, then A, B, and C together can finish the work in?

12. A and B can complete a work in 8 and 12 days respectively. They work together for 4 days. Remaining work will be completed by B in?

13. A train crosses a platform 200 m long in 25 seconds at speed of 72 km/h. Length of the train is?

14. If 15 men can reap a field in 6 days, then 9 men will reap it in?

15. A and B together can do a work in 12 days. B alone can do it in 30 days. A alone can do it in?

16. A train 180 m long passes a pole in 9 seconds. Its speed is?

17. A can finish a work in 10 days and B in 15 days. If they work on alternate days starting with A, the work will be completed in?

18. A can build a wall in 12 days, B in 16 days. Together they work for 4 days, then B leaves. Remaining wall will be built by A in?

19. A tank can be filled by a pipe in 8 hours. It is emptied by another in 12 hours. If both pipes are opened together, tank will be filled in?

20. A and B together can do a work in 10 days. If A alone can do it in 15 days, B alone can do it in?

21. A leak can empty a full tank in 9 hours. If a pipe fills the tank in 6 hours, the net time required to fill it when both are open?

22. A can complete work in 18 days, B in 24 days. They worked together for 6 days, then B left. Remaining work was completed by A in?

23. A alone can complete a work in 16 days, B alone in 24 days. They work together for 6 days, then B leaves. Remaining work will be completed by A in?

24. If 12 men can complete a job in 8 days, then how many men are required to complete it in 6 days?

25. A train of length 200 m crosses a standing man in 10 seconds. Its speed is?


 

Malik Tahir

Greetings, learners! I'm Tarry Malik, your guide to conquering the world of Exams prep and Online studies. Let's navigate the textbooks together, share study hacks, and make your educational journey a breeze.

3 Comments

  1. question 2 and 3 both wrong in qestion 2 7.5 should be radius instead of circumference to make ans 132 and question 3 correct ans is 84 minutes( 1 hour 22 minutes) which is not in the answer sheet